Tag Archives: Long Lots School Building Committee

Long Lots Update: What’s Happening, And When

For over 2 years, the renovation of Long Lots Elementary School was one of Westport’s most controversial issues.

Since June — when the Long Lots School Building Committee received unanimous approval from every town board and commission to move ahead with the design development, construction documents and construction of the new Long Lots and Stepping Stones Preschool project — we’ve heard very little.

Long Lots Elementary School — as it looks now …

But that does not mean nothing’s happening.

Yesterday, the LLSBC issued an update.

They said they have met with neighbors to review the first phase of the project. Once construction actually begins, they promise “more frequent updates.”

The project has been broken into 5 phases for state approvals. This will allow the geothermal drilling portion of the project to begin, while construction documents for the new building are in process.

“This will allow the construction manager the space to better stage the project,” the committee says.

… and one look at the future …

They note that the 5 phases of state approvals will not always align with the construction schedule. Those phases are:

Geothermal wells (underway): Approved by the state Office of School Construction to go out for bids last August. A contractor was selected.

The area has been fenced; construction trailers and temporary electric service has been installed; the lower soccer fields have been stripped in anticipation of drilling, and topsoil has been screened.

Drilling and installation of the geothermal wells is currently taking place on the lower soccer fields. Each of the 100 wells is 500 feet deep. Eighty have already been drilled. Completion is expected next month.

Pre-purchase of electrical switchgear and generator (underway): Approved by the state Office of School Construction to go out for bids last September. A contractor was selected.

The generator and electrical switchgear are being purchased early, to avoid nationwide supply chain delays of up to 17 months. This equipment will be installed during the construction of the new school.

… plus another.

Construction of the new Long Lots Elementary and Stepping Stones Preschool (next): Construction documents have been reviewed by the state Office of School Construction, and were released for bid in December.

Received bids will be evaluated in March. It is anticipated that construction will begin in April, with excavation for footings and foundations.

Furniture, fixtures and equipment: This will be submitted to the state for approval in late 2026. All furnishings will be new, and purpose-designed for the school. Delivery will align with the end of the new school construction. It is anticipated that no student-related equipment will be moved from the current building.

Demolition of the old school; construction of parking lots, athletic fields and Playgrounds (Late 2027; into 2028): Demolition of the current school will begin after the new one is occupied. Playgrounds, parking lots and athletic fields will follow the demolition of the old school.

The LLSBC notes that the upcoming bid process will help establish a more defined construction timeline.

Long Lots site plans.

The committee expects to meet with the Board of Education, and the faculties of Stepping Stones and Long Lots, to review the interior finishes in mid-February.

The LLSBC plans to have another neighborhood update prior to the start of the new building construction.

They will provide the Architectural Review Board with an update, followed by a town-wide project presentation in late February.

(For the Long Lots School Building Committee’s page on the Westport town website, click here.)

(“06880” keeps a close eye on Long Lots — and all our schools. If you appreciate our coverage of education — and/or anything else on your hyper-local blog — please click here to support us. Thank you!)

Long Lots Vegetation Clearing: Building Committee Responds

This morning, “06880” reported on the first day of construction for the new Long Lots Elementary School. Homeowners just south of the property reported that carefully drawn plans had been disregarded, resulting in clearance of an estimated 6,000 square feet of mature vegetation and growth beyond the construction road.

This afternoon, the Long Lots School Building Committee responded. They told “06880”:

This statement is intended to address the story regarding the over-clearing of vegetation on the Long Lots campus in close proximity to a resident’s home.  We would like to explain what happened, and what steps are being taken to address the situation.

Despite the extensive planning and multiple site visits conducted to review the area on the east side of the Long Lots campus which was designated for limited clearing, some additional vegetation beyond the intended scope was mistakenly removed by the contractor as the road for construction vehicles was installed.

It was a mistake and should not have happened. The issue has been reviewed extensively with all involved to ensure mistakes like this are not repeated.

Pre- and post-construction views.

To remedy the situation, a plan has been developed to plant a large evergreen buffer (in addition to similar plantings which will be planted on the site in the future) in the affected area within the next 1 to 2 weeks.

The homeowner who is most affected by this over-clearing will be involved in the placement of the trees in advance of the plantings. The Building Committee’s project manager has already been in contact with the homeowner.  A separate letter to Planning and Zoning which details this remediation is also in the process of being delivered.

While we sincerely regret this error at the start of the new school construction process, we also see the proposed remediation as an opportunity to improve the plans for the final result. Upon project completion, the landscape buffer between the school property and the residence closest to the east side of the campus will be enhanced over the previous mix of unkept trees and the initial proposed single layer of evergreens.

Again, we regret the mistake and we will work to ensure it is not repeated.

Sincerely,
The Long Lots Building Committee

Long Lots Neighbor: Demolition Goes Far Beyond P&Z Approval

For 3 years Julianne Mulvey attended meetings, made phone calls and wrote letters about the Long Lots Elementary School building project.

As the closest neighbor south of the Hyde Lane site — with a home abutting the former Community Gardens — she wanted to be sure that her rights as a property owner were considered.

She and her husband Fran made compromises. They also made sure the Long Lots School Building Committee included elements like buffer zones in the design.

The first phase of construction began last week. On the very first day, carefully drawn plans were disregarded.

The buffer area, with before-and-after photos.

Specifically, the couple said in a letter Monday to the Planning & Zoning Commission:

Representatives of the LLSBC assured us that clearance along our property line would occur at the greater of the flagged 25 feet from property lines or areas essential to the approved site plan. That is not what transpired.

The most egregious clearance has occurred between the main construction road and our front yard. We were explicitly assured by the LLSBC that this area would remain as undisturbed as possible, while still allowing access to the site.

While the construction road was positioned the maximum distance from our home, the demolition crew nonetheless destroyed an estimated 6,000 square feet of mature vegetation and growth beyond the construction road — our home’s primary buffer from the project site.

This area is not part of the construction plan or existing future plans for the site and did not need to be cleared for the project to proceed. The fact that the area lies outside the fence enclosure of the construction site further underscores this point: It did not need to be destroyed.

Despite our repeated and consistent concerns voiced over the past 3 years, the LLSBC proceeded in direct opposition to both its own assurances and the conditions of P&Z approval, which specifically required that our property be taken into consideration.

In addition, certain areas were cleared within as little as 15 feet of the property line — though a walkthrough with the LLSBC identified flags at 25 feet that were meant to preserve the buffer.

The effects on their quality of life — and property values — have been devastating.

“We have spoken repeatedly in the last 12 months about our fear that demolition would occur without a town representative on hand for us to speak with immediately,” the couple said in the letter to the P&Z.

On the first day of construction, there was no representative of the town on site — “only construction workers doing their job with understandably no authority to speak with us.”

After seeing the letter, “06880” reached out to Julianne Mulvey.

She said that on Monday, Susan Chipouras — project manager for the LLSBC — knocked on their door. (Mulvey noted that Chipouras had tried to contact them earlier.)

Chipouras first blamed a utility company. Mulvey said that they had removed only one tree.

Chipouras acknowledged the gravity of the clearance, and implied it was a third party mistake.

“It was the first day of a $100 million project,” Mulvey said. “And no one was there from the LLSBC to oversee the removal of this sensitive buffer area.

“On the first morning the project began, everything we had been promised was gone.”

(Photos and graphics courtesy of Fran and Julianne Mulvey)

Before last week, the Mulveys could not even see the school. Now they live adjacent to a construction zone.

And they can see everything.

“Our skepticism regarding the LLSBC’s promises to take ‘only what is necessary’ (a quote from chair Jay Keenan during a formal walkthrough with neighbors in August) regrettably, has been validated,” the Mulveys’ letter said.

“We no longer have confidence in the town’s ability to manage this project.”

Chipouras proposed plantings to minimize the effect of the removal.

But, Mulvey said, “the damage is done. It is on the LLSBC and the town to fix this mistake.”

 

[OPINION] Community Garden Chair Says: Build New Long Lots Now!

Lou Weinberg is chair of the Westport Community Gardens, and director of the Long Lots Preserve. He writes: 

To the parents and teachers (and kids!) at Long Lots Elementary School, and to the rest of our fine community:

I believe it is time to move on, and build a new school at Long Lots without any further delay.

I am a recently retired, former public school teacher. I understand the value of education. I spent 2 decades promoting that philosophy to a couple of thousand students.

Lou Weinberg spent 2 decades in front of a classroom. Not long ago, he addressed the Westport Rotary Club.

I loved teaching, and I think I was pretty darned good at it. That’s what my students and most of their parents have told me. I’ve had a mutually positive relationship with the vast majority of kids I have shared a classroom with.

I worked in a school that had constant leaks, mold, and no air conditioning on the second floor, under a black tar flat roof.

Broken floor tiles were a constant issue. Bathroom sinks and urinals leaked. Concrete stairways outside the school were severely dilapidated. The list is a lot longer, but you get the picture.

I want you to hear this from me.

I firmly believe that a new school is severely needed at Long Lots. I know it should be done as expeditiously and as economically as possible.

I want the children in this town to have the best education, from the best teachers, that they possibly can. No doubt that is currently the case, and will be the case, for as long as there are schools in this district.

I am blown away by elementary school teachers, who serve many different bosses (including the little ones in the classroom) every single day, fielding hundreds of different requests, problems and issues, while preparing and delivering instruction on several different subjects, in several different ways.  I know it helps exponentially to have the right environment in which to perfect their craft.

I completely understand the needs of students served by Stepping Stones too. I have had hundreds of students in my career with different and special needs, requiring differentiated instruction and a whole lot of love. Places like Stepping Stones are worth their weight in gold to the students they serve, their parents and ultimately, to the community they live in.

The original Long Lots Junior High School opened in the mid-1950s.

Of course I have advocated for preserving and protecting the Westport Community Gardens, the Long Lots Preserve, and the green open space adjacent to the school.

My advocacy has never been about opposing the creation of a new school. I believe that the school construction should have begun already, and that the process should have included consideration for the gardens and preserve.

Unfortunately, it did not.

This statement should not be taken to mean that I and the many people in town who support having a community garden, preserve and green open space are giving up on our request that an equitable site for a new garden be found.

I have the utmost confidence in Paul Leibowitz, and the rest of the Planning & Zoning Commission’s thoughtful and diligent work on this issue. They will render a decision, and we will all move forward.

I believe it is time to move on and build a new school at Long Lots without any further delay.

Thank you for reading this.

(“06880″‘s Opinion pages are open to all Email submissions to 06880blog@gmail.com.)

[OPINION] Lou Weinberg: Current 8-24 Destroys Gardens And Preserve. Approve An 8-24 Where Everyone Wins.

Lou Weinberg — chair of the Westport Community Gardens, and director of the Long Lots Preserve — addresses this open letter to the Planning & Zoning Commission:

You’re being asked to approve an 8-24 that removes the Community Gardens from the Hyde Lane property, after approving an 8-24 that kept them on site.

You’re being asked to approve an 8-24 that destroys and removes the very successful Long Lots Preserve.

You’re being asked to approve an 8–24 that supports, nearly corner to corner, the clear-cutting of all the older tree growth that has existed on this property for generations, removing a valuable buffer for homeowners adjacent to the property.

Dozens of trees including black cherry, black walnut, pine, spruce, maple and others make up this green open space.

Some of the dozens of trees in the Long Lots Preserve.

Please do not approve an 8-24 without a provision to provide equitable space for a new community garden, either on the Hyde Lane site (post construction) or at Burr Farms Fields.

The Hyde Lane site can be done simply, easily and expeditiously with a new site plan that rebuilds the garden in its current location after construction. It could be surrounded by an 8-foot fence and a curb cut with a separate entrance to the Gardens that completely separates that space from the school.

Alternatively, that acre of space can be used for new fields and an equitable garden relocated to Burr Farm Fields.

In addition, please do not approve an 8-24 without provisions for protecting the Long Lots Preserve. If you deem it truly necessary to approve a site plan that replaces the Garden with fields, at least limit the size of the fields to the space that the current garden occupies. Do not allow the building committee to mow down the rest of what limited green open space would be left there.

An alternate site plan includes a community garden, maintains the Long Lots Preserve, and keeps ball fields. The garden has its own curb cut and driveway, separated from the school parking lot by an 8- foot fence.

The Long Lots Preserve is a model of suburban open space environmental rehabilitation that was unanimously approved by the Board of Selectwomen.

100% of the Preserve was community funded. It was developed by local businesses, organizations and residents.

Second Selectwoman Andrea Moore said during the Preserve approval process, “I think this is the type of volunteerism which should be encouraged …. Here to help. Your work is really what this town should be all about.”

Representative Town Meeting moderator Jeff Wieser called the Long Lots Preserve plan “an environmental win for the town.”

Westport’s green space is rapidly dwindling, due to rampant development. This side of town in particular has seen a significant decrease in tree cover. There is extremely little green open space left.

Community Gardens and adjacent Long Lots Preserve (marked by Xs), slated for removal under the current 8-24.

The non-school related part of this 8-24 flies in the face of the sustainability portion of the town’s Plan for Conservation Development, Net Zero 2050 and Westport’s 2021 Tree City USA designation.

The Plan of Conservation Development states, “Open space helps protect natural resources; provide flood storage, wildlife habitat, and tree canopy; enhance overall community appearance; and enhance the quality of life of residents and visitors. Westport residents value the preserved open space areas that add to the overall beauty of the community and want to: maintain the open space areas we have, add more open space areas as opportunities arise… Preserving open space will help make Westport a more sustainable community by retaining natural spaces and sustaining environmental health.”

By destroying the Westport Community Gardens, the Long Lots Preserve and the additional forested acreage, we are doing exactly the opposite of what we teach our children in school.

Chicakdee, in the Long Lots Preserve. (Photo/Lou Weinberg)

Current science standards focus on how the environment works, the systems that sustain healthy environments, and the human impacts on our rapidly degrading ecosystems.

The parcel of land that will be destroyed if you approve this 8-24 supports incredible biodiversity from very healthy populations of organisms native bees, honey bees, butterflies, moths, fireflies, dragonflies to tree frogs, short-tailed weasel, red squirrel, rabbit, harmless garter snakes etc.

This kind of biodiverse green island is nearly gone in Westport. A clean, healthy environment with a hands-on environmental educational benefits is a legacy we can, and should, leave for our children.

This administration and the Long Lots School Building Committee have moved the goal posts consistently for over 2 years. From keeping the gardening community out of the discussion altogether (see former Parks and Recreation cirector Jennifer Fava’s “Oops,  I guess they found out”) to “It’s just lines on a map” to “We’re going to keep you on the property” to “You won’t be able to use the gardens for a year” (then “2 years”) to “We’re going to move you to (the unviable) Baron’s South” to “We’re going to put you on the property, but you won’t have access to the Gardens for 3 years” to “We’re going to restrict your hours” to 2 years of our first selectwoman’s State of the Town addresses claiming she would keep the Gardens on the property, to an 8-24 that puts them in some capacity on the property, to another 8-24 removing the gardens from the property altogetherm to the latest proposal to kick this can down the road and figure it out during yet another study (the Parks Master plan).

Long Lots Elementary School site plan. Community Gardens and Long Lots Preserve are circled at left.

I know that the P&Z and the more well-informed residents of our community know that the 120 families that represent the Westport Community Gardens have not delayed progress towards replacing the school by one second.

I hope that those who have paid attention to this effort to build an improved school recognize that the people who support the Garden and Preserve (most of whose children went through our school system and who have paid taxes here for decades) have always promoted building a school, while valuing and protecting what has been created on the 4 acres of open space adjacent to the school.

Destroying the Gardens and using it for staging and then ballfields was not part of the Board of Education specifications in the first place.

The current site plan’s proposed ballfields will cover this lot nearly from corner to corner, and have nothing to do with a new Long Lots Elementary School. This was an add-on by the 1st Selectwoman and building committee.

In addition to the Community Gardens (foreground), trees in the Long Lots Preserve could be removed as part of the school project.

Before Westport Community Gardeners were vilified and demonized as a political tactic to remove the Gardens from the property, schools superintendent Thomas Scarice stated his desire to keep the Gardens/Preserve green open space as a buffer between the school and the adjacent residents.

The destruction of the Westport Community Gardens and Long Lots Preserve, and the refusal to replace them, is not and should not be under the Long Lots School Building Committee’s purview.

Please do not allow the Long Lots School Building Committee to be a de facto land use planning entity. Their charge is to manage getting a school built. Their overreach should be checked by this commission.

Please stand up to the bulldozers and approve an 8-24 where everyone wins; the Long Lots kids, teachers, neighbors, our senior residents, community gardeners, and the environment.

Thank you for your consideration, and for the significant amount of time and effort you put into making decisions that you believe will benefit our town.

(“06880″‘s Opinion pages are open to all. Email submissions to 06880blog@gmail.com.)

[OPINION] Long Lots Project: With Many Questions, More Vetting Needed

Attorneys Mark and Valerie Seiling Jacobs have lived in Westport for more than 25 years. They have followed the Long Lots Elementary School building project closely. They write:

On May 16, the Long Lots School Building Committee filed 2 documents with the Planning & Zoning Commission: a new 8-24 request (presumably because the existing approval requires that the Community Gardens remain on site, which is no longer the plan), and a request for site plan approval for the entire project.

Almost immediately, the project began to appear on the agendas of other town bodies, including the Board of Finance, Flood & Erosion Control Board, Representative Tonw Meeting Finance Committee, Conservation Commission, and full RTM.

Eight critical meetings are now expected to take place in the space of the next 10 days. Given the tight timetable, some of the meetings are being combined. Others are scheduled to take place on the same night.

This of course has prompted many people to ask: Why is the schedule so compressed and rushed? After all, this is the largest expenditure in town history.

Preliminary designs for Long Lots Elementary School.

According to Eileen Flug, the assistant town attorney who was quoted in the Westport Journal, the rush was due to a “realignment” of 2 state agencies that moved the deadline for state bonding applications up to June 30, and the fact that the town had only learned of this on May 16.

In that same article, however, Jay Keenan, committee chair, attributed the rush to the fact that he had not realized that the Town Charter contains a 14-day window for residents to file a referendum request, meaning that the effective deadline was actually June 16.

Neither of those explanations, however, holds water.

First, we have been unable to find any such realignment of state agencies. Nor have we been able to find any evidence that the state deadline changed. (We’ve asked Ms. Flug to provide the backup for her statements, but, so far, we’ve received nothing.)

And second, even if we accept Mr. Keenan’s version, it begs the question: Why did the committee wait so long to file to begin with?

If they knew that they only had until June 30, then why did they wait until May 16 — a mere 45 days from the deadline — to begin securing the necessary local approvals, when they knew they needed to appear before 6 separate town bodies?

Long Lots School Building Committee members, meeting in 2023.

One explanation is that the committee is not being honest, that they somehow missed the fact that everything is due on June 30 and are now using the 14-day window to obscure their mistake.

Given this committee’s historical willingness to blame others (usually, the gardeners) for problems of their own making, it wouldn’t be surprising if that turns out to be the answer.

There may, however, be an even more sinister explanation: that the committee deliberately delayed filing specifically to truncate the review process, limit public participation, and deny other boards the opportunity to conduct the type of in-depth analysis that a project like this requires.

Such a strategy would be consistent with this administration’s modus operandi, which seems to be based on rushed requests coupled with a “sky is falling” mentality.

The repairs to the Mill Pond walkway and flood gates are a perfect case in point. The RTM and public were repeatedly warned by the administration that if they didn’t go along with the plan, the town could lose the federal money. (Never mind that the place had been falling apart, for years or that we’d had a long time to draw down the ARPA funds.)

In this case, however, rushing the process carries even greater risk, given the cost of the school and the topography of the site. As one resident correctly pointed out, the “site is chock full of flooding, wetlands, inland waterways, abutting residential housing, difficult terrain and contaminated soil.” And it is no secret that this area is already plagued by water issues.

The committee keeps telling the neighbors not to worry. “Trust us,” they say. But this committee has not earned the public’s trust. Their vague assurances are small comfort to a homeowner who is facing the prospect of a flooded basement or worse.

Muddy Brook flooding, near Long Lots School. (Photo/Peter Swift)

We urge our Conservation Commission and Flood & Erosion Control Board to examine the application carefully — to kick the tires when it comes to drainage and environmental issues.

We all know that the storms keep getting worse. And this project calls for a doubling of building coverage during construction and the permanent loss of vegetation that previously acted as a buffer and sponge for runoff.

Please do not be lulled into thinking that the old way of managing water will suffice. One-hundred-year-storms are now arriving like clockwork. We need you to step up and protect neighbors, even if that means imposing novel or extra protections.

And the same holds true for P&Z. We need our commissioners to ask hard questions and demand fact-based answers — not settle for off-the-cuff responses.

Does, for example, the new school really need 30% more parking, which would vastly increase the amount of impervious material? The traffic consultant didn’t think so, but he appears to have been persuaded to say otherwise by someone involved in the process.

Long Lots Elementary School, with current parking. (Drone photo/Brandon Malin)

Similarly, if the committee is truly committed to using natural grass for the fields, then why do the plans call for the type of underground drainage typically used with artificial turf?

Putting aside the PFAS and microplastic risk associated with artificial turf (which, frankly, is pretty difficult to ignore), this particular site is spectacularly unsuitable for artificial turf given the ongoing drainage issues and the fact that artificial turf impedes the natural infiltration of water.

In fact, the EPA classifies it as impervious and there is now a call to deny LEED certification to any site with artificial turf. In any event, P&Z needs to get to the bottom of these and other troublesome issues and questions.

We all want a better school for our children. But this project needs to be properly vetted by our various boards and commissions.

If this process is not handled properly, we fear that residents will take advantage of another provision in our Charter — one that gives 20 electors (or 2 RTM members) 30 days to appeal any Conservation or FECB decision to the RTM. (How Mr. Keenan intends to square that appeal period with the June 30 deadline remains to be seen.)

Were an appeal to ensue, this project could be indefinitely delayed. And the Committee members will have no one to blame except themselves.

(“06880″‘s Opinion pages are open to all readers. Please send submissions to 06880blog@gmail.com.)

Long Lots Approvals Face Tight Deadline For State Funds

For 3 years, the proposed new Long Lots Elementary School project has lumbered along.

The building committee planned (and planned and planned). The Community Garden was removed, moved back, moved again. Athletic fields morphed from baseball to all-purpose, grass to artificial turf. 8-24 (town municipal use) permits were filed and refiled. Construction — originally hoped to begin last year — remains on the horizon.

Suddenly though, the lumbering pace will become a race.

Preliminary plans for the new Long Lots Elementary School.

Toni Simonetti — a gardener who is following the project with a close eye — notes that the deadline for a Connecticut funding grant application is June 30.

“The state can reimburse a town anywhere from 10-70% of the cost to replace a school with a new one. (Westport likely to be on the low end of that range.),” she reports.

She’s compiled a master list of meetings that must be held — and votes taken — before the funding application deadline, 34 days from now.

A recent schematic for Long Lots School.

For example, the Planning & Zoning Commission must hear testimony on a new 8-24 plan, along with a new special permit/site plan.

The Conservation Commission and Soil & Erosion Control Board must both grant approval for the area — which includes wetlands and a brook — in order for the state grant to be approved.

Financing approvals for the $98 project are still ahead, too.

Upcoming meetings include:

  • June 3: Representative Town Meeting (RTM) first financial review (7:30 p.m., Town Hall).
  • June 4: Conservation Commission and Flood & Erosion Control Board joint meeting (Zoom, 7 or 7:30 p.m.).
  • June 5: Board of Finance first meeting (7:30 p.m., Town Hall).
  • June 9: Planning & Zoning Commission, 8-24 vote and site plan/special permit approval (Virtual, 6 p.m.).
  • June 10: RTM Finance Committee vote (7:30 p.m., Town Hall Room 201).
  • June 11: Board of Finance vote (7:30 p.m., Town Hall).
  • June 12: RTM expected final vote (TBD).

(Toni Simonetti’s full Substack on the Long Lots project can be read here. Hat tip: Kristin Schneeman.)

Roundup: Hamlet Meeting, E-bike Safety, Free Saplings …

After the recent Zoom-bombing of the Planning & Zoning Commission meeting — an attack that included pornography, Nazi symbols and the video of a beheading — the next meeting will be in person.

It should draw a large crowd.

The P&Z agenda for next Monday (April 28, 6 p.m., Town Hall auditorium) is about the proposed Hamlet at Saugatuck retail/residential/hotel/marina development.

The public hearing includes input from residents.

A 65-day extension has been granted for this phase of the regulatory process. The final date for a decision is now June 18.

Aerial rendering of the Hamlet at Saugatuck proposal.

=================================================

Another meeting discusses another long-debated project: the new Long Lots Elementary School.

The Building Committee meets tonight (6 p.m., Town Hall Room 201/201A) for a project update. There will be time for public comment.

Three views of a possible new Long Lots Elementary School.

===============================================

E-bikes are e-verywhere.

To raise awareness about safety, the Westport Police Department is sponsoring a community forum.

The May 13 event (6:30 p.m., Town Hall auditorium) will cover rules and regulations (for riders and motorists), street awareness, and tips and resources for all ages. A Q-and-A session will follow.

The evening will feature law enforcement officials and safety director Charles Foster of SCBC Safe Rides.

Class 3 e-bike.

=================================================

Speaking of transportation: The Representative Town Meeting (RTM) Transit Committee and Westport Transit District meet jointly tonight (Tuesday, 7 p.m., Westport Library Room 210).

The agenda includes:

A recommendation to the RTM on the 2025-26 budget request for railroad parking, including a discussion of railroad parking permit revenues.

A recommendation to the RTM on the 2025-26 Transit District budget.

A recommendation to the RTM on a supplemental appropriation of $55,000 for transportation services for the elderly, and people with disabilities.

A discussion on expanding Wheels2U service to the Senior Center, Farmers’ Market, and Jesup Green/Westport Library, beginning next month.

==================================================

Yesterday’s Roundup gave an incorrect location for the memorial to Max Harper.

It’s at the western end of South Beach, near the trees and benches across from Ned Dimes Marina.

It’s a beautiful spot, for a loving tribute.

The Max Harper memorial stone, on Compo’s South Beach. (Photo/Pam Docters)

=================================================

There may be no such thing as a free lunch.

But there are free tree saplings.

the Westport Tree Board will give them away this Friday (April 25, 3 to 5 p.m., Town Hall back parking lot).

The gifts are in honor of Arbor Day. There’s one per family — choose from Virginia pine, river birch, red cedar or lilac.

Tree Board sapling giveaway, in 2022.

===============================================

A reminder: One of the most inspiring — and fun — galas of the year is this Saturday.

The A Better Chance of Westport Dream Event raises funds for the non-profit that creates educational opportunities, and changes lives, for exceptional young men from less advantaged communities.

As always, the highlight will be speeches from the graduating seniors, and an ABC alum. This year’s returning grad is Yoel Hooper-Antunez. Click here to read his amazing back story.

The Dream Event also includes excellent food and drinks, a silent auction, and a chance to hang with some of the most accomplished young people in town. Click here for tickets, and more information.

The current A Better Chance of Westport scholars.

================================================

Also at the Library: the return of Andrew Wilk’s Medical Series.

The topic for 2025 is oncology. Longtime local internist Dr. Robert Altbaum moderates each of the 4 sessions, and introduces experts.

Tonight (Tuesday, 7 p.m.), Dr. Richard Frank, chief for clinical and translational cancer research at Nuvance Health, describes recent advances in cancer, including chemotherapy, targeted DNA treatment and immunotherapy, and explores the diagnostic, therapeutic and psychological challenges of treating advanced cancer

Dr. Robert Altbaum

===============================================

Dylan Robbin knows hoops.

Last week, the Staples High School freshman was featured on the House of Highlights YouTube channel.

The 90-minute segment included a debate between 10 Gen Z sports podcasters and Jermaine Womack, who runs the popular YouTube channel Chill Town Hoops.

At 14, Dylan was the youngest participant by at least a decade.

A clip of his conversation with Womack about whether Steph Curry is the best point guard of all time went viral on Instagram.

Click below to see the full debate. You can follow Dylan on Instagram and TikTok: @drsportstakes.

==================================================

Frank Rosen is probably the 50th reader to send a photo of the bald eagle that perches regally on the communications tower at the Westport police station.

But he’s the first to realize — without me telling him — that the bird is a wooden fake.

(Photo/Dylan Rosen)

“We killed about 30 minutes in the beautiful sunshine, taking in it’s majestic beauty,” Frank says.

“I waited so long for it to fly away — only to realize it’s not real.”

No one else who sent similar images to “06880” over the past month realized — until I told them — that the reason the eagle stood so still for their photo is because it never moves.

Reactions range from laughter to anger. Most common, though, is embarrassment.

To whoever placed America’s national bird atop the tower: well played.

=================================================

A new guest has been added to CT Against Gun Violence’s annual spring benefit “Be the Hope” luncheon (May 15, 11:30 a.m., The Inn at Longshore).

The headline speaker is Rob Wilcox, former deputy director of the White House Office of Gun Violence Prevention.

He’ll join Sandy Hook youth activist Matthew Holden, who will discuss his work. Click here for tickets.

==================================================

Tulips bloom around the Minute Man, in today’s “Westport … Naturally” feature.

(Photo/Sunil Hirani)

Up next for our town symbol: The 248th anniversary of the Battle of Compo Hill.

This is not some random monument. Our Minute Man commemorates the Battle of Compo Hill — fought 248 years ago, this week.

==================================================

And finally … in honor of the wooden eagle behind the police station, which does not fly anywhere:

(If you click here to support “06880,” your hyper-local blog, our heart will soar like a — dove. Thank you!)

Public Gets First Long Lots Look

The new Long Lots Elementary School will look nothing like the old one.

That was one takeaway from Thursday night’s “reveal.”

More than 2 dozen residents jammed a Town Hall conference room, to watch the Planning & Zoning Commission examine the Long Lots School Building Committee’s plan for 127,000-square foot, $100 million structure. It would be built approximately where the current upper baseball diamond lies.

Planning & Zoning Commission and Long Lots School Building Committee members meet at the conference table, as spectators fill the Town Hall room. (Photo/Toni Simonetti)

Among the features: peaked New England-style roofs, a stream near the entrance, and a courtyard.

Three views (from top): from the east (Hyde Lane), south and north.

What’s missing is a site for the new gardens, which would be displaced by a new athletic field. Without that — promised in the previous 8-24 plan — P&Z approval is in doubt.

A site for the gardens could ultimately be found on the Hyde Lane property, which also includes parking. If there is a new garden site elsewhere, a revised 8-24 may be required.

The proposed new school. From the left (south) to the right (north): athletic field, parking, school, lower athletic fields. Hyde Lane is at the bottom (east).

The courtyard (shown above) is envisioned as a place for outdoor classes and other gatherings. It will also provide natural light for the building.

(“06880” reports regularly on education, town politics, their intersection, and much more. Please click here to support our work. Thank you!)

Selectwoman’s Update: Hamlet, Long Lots, Meetings And More

The latest edition of “Westport in Focus” — 1st Selectwoman Jen Tooker’s regular newsletter to residents — landed in email inboxes earlier today.

For those who did not open it — and “06880” readers outside of Westport who did not get it — the highlights include:

A note about the newly redesigned Selectwoman’s Office page on WestportCt.gov: Selectwoman’s Office Home.

IT director Eileen Zhang and Tooker’s staff have spent quite a while redesigning this, and other departments’, home pages. The result: greater visual appeal, and ease of use.

Screenshot of the new Selectwoman’s Office page.

The tentative pubic meeting timeline for the Hamlet at Saugatuck project. It includes

  • Planning & Zoning Commission meetings: April 7, and late April and May (NOTE: There is no Hamlet discussion tonight, March 31)
  • Flood and Erosion Control Board: April 2
  • Waterline Protection Line Ordinance and Conservation Commission: April 23-April 30
  • Historic District Commission:  TBD
  • Board of Selectwomen, acting as the Traffic Authority: TBD

The Hamlet at Saugatuck proposal for Railroad Place.

An update on the Long Lots School Building Committee.

Tooker reports that regular meetings continue. “Providing there are no other delays, it is anticipated that groundbreaking will occur this year, with an anticipated move-in date in September of 2027,” Tooker says.

The LLSBC recently received approval for awarding contracts for MEP commissioning aervices, building envelope commissioning services and geothermal test well services.

The project now enters the design development phase, with more detailed plans, elevations and finishes. This is expected to be completed in the next several weeks.

Meetings with the Board of Finance and Planning & Zoning Commission are being scheduled, and are anticipated to take place in the first part of April.

The School Building Committee will also schedule a work session with the Architectural Review Board, a meeting with the Representative Town Meeting  Education Committee for an update, and meetings with all funding bodies and the full RTM (plus committees) over the next few months.

The LLSBC also hopes to schedule a town-wide charette during the design development phase.

See Long Lots School Building Committee page on the town website for all updates and relevant documents.

A very preliminary plan for Long Lots Elementary School.

✔ Upcoming dates of interest:

Tuesday, April 1: 4th quarter taxes due (May 1 deadline without penalty; click on Tax Collector’s Office.

Thursday, April 3 (11 a.m. to 2 p.m.): Free car seat safety inspections at Police Headquarters (50 Jesup Road).

Saturday, April 5 (9 a.m. to 2 p.m.): Household hazardous waste collection at Greens Farms railroad station; click on Household Hazardous Waste Day.

Sunday, April 13 (3 p.m.): Tulip sculpture dedication at Grace Salmon Park.

April 21-26: Community Build Week at Compo Beach Playground; click on Compo Beach Playground.

Saturday, April 26: Town Clean-Up Day – information soon from the Parks & Recreation Department.

Tuesday, April 29 (7:30 p.m., Town Hall auditorium): Traffic & Pedestrian Safety Task Force meeting.

Thursday, May 1: First day parking emblem requirement for beach access; click on Parks & Recreation.

In one month and a day, you’ll need a sticker to park at town beaches. In the meantime, crews work to get them ready. (Photo/Richard Fogel)