Construction work on the Merritt Parkway — from before Exit 41 to beyond Exit 42 — has been going on, it seems since dinosaurs and Studebakers roamed the earth.
The $56 million project includes upgrades to pavement, guardrails and drainage, and restoration of “historic concrete.”
It’s bad enough for drivers (who must navigate frighteningly tight concrete barriers, including on- and off-ramps) and residents (who have endured noise, dust and the destruction of acres of woodlands).
Concrete barriers and no shoulders make driving on the Merritt Parkway a life-in-your-hands experience. (Photo/Bob Mitchell)
But right now, work seems stalled. What’s happening? When will it resume? And how long will it take?
I asked Jonathan Steinberg, Westport’s state representative. He sits on the Transportation Committee, and lives not far from the endless mess.
A Department of Transportation representative told him that right now, there’s a restriction: Work cannot proceed after 11 p.m.
Because of that, the contractor — Manafort Brothers — has stopped work altogether. They say that with just a 3 1/2-hour night window, the project is not feasible. (Work cannot begin until 7:30 p.m., after rush hour.)
However, the DOT official continued, “I agree that the noise we are making now is probably the worst, and this is only Southbound there is another opposite in the Northbound shoulder.”
DOT is “looking at various options that include reducing the amount of rock removed and beefing up the guide rail. Compensating the Contractor for his lost production. Utilizing day time lane closures. Allowing full shift work but on limited nights.”
However, he concluded — ominously for all — “as of today we do not have a solution.”